Update: Time needed for work: 1) Single Door Conversion: 5 days 2) Repaint: 3 days 3) Hanover/Mobitec dest fittings: 1 day 4) Hanover/Mobitec NSA fittings: 1 day 5) Seat Retrim: 1 week 6) Interior Panel re spray: 3 days 7) New floor: 2 days 8) Exhaust upgrade: 2 days 9) Engine rebuild: 4 weeks 10) New gearbox: 3 days 11) General mechanical repairs: 1-5 days 12) Exterior panel repair: 1-3 days Please note that 1) to 7) can be completed together